Work in Progress History Report screen

Use the Work in Progress History Report screen to create a report of projects, cost codes, and cost types for which work in progress entries exist within the specified date range. You can print or save this report.

Note: To open the Work in Progress History Report screen, click Projects > Reports > Work in Progress History Report in the All Tasks pane.

You can control the output of the Work in Progress History Report by entering details in one or more of the following fields on the Options tab:

  • Select Format - If you have modified the format and layout of this report on the Modify Reports screen, click to select the version to use for this report. If you haven't modified the report, this field doesn't appear.

  • Report From Date - Enter the start date for the report, click to select the date from a Date Picker, or click to enter a Date Formulas. If you want to save the information in the date field when you save the report options, you must use a date formula.

  • Report Through Date - Enter the end date for the report, click to select the date from a Date Picker, or click to enter a Date Formulas. If you want to save the information in the date field when you save the report options, you must use a date formula.

  • Company - Click to select one or more companies for the report. If no companies are selected, all companies appear in the report.

  • Division - Click to select one or more divisions for the report. If no divisions are selected, all divisions appear in the report.

  • Customer - Click to select one or more customers for the report. If no customers are selected, all customers appear in the report.

  • Project Classification - Click to select one or more project classifications for the report. If no classifications are selected, all classifications appear in the report.

  • Project Manager - Click to select one or more project managers for the report. If no project managers are selected, all project managers appear in the report.

  • Project - Click to select one or more projects for the report. If no projects are selected, all projects appear in the report.

  • Project Status - Click to select the project status for the report. Select Both to show both active and inactive projects in the report.

For information on running the report, see Run and Print Reports.