Retention Billings From Subcontractors

The example given here shows you the effects of changing the retention amount on an Accounts Payable subcontract that has already been billed.

Example:

$10,000 subcontract

10% retention

01/31/05 Subcontractor bills $7,000

Enter A/P Vendor Invoice Entry for subcontract. Invoice amount = $7,000

$700 retention defaults in A/P Vendor Invoice Entry and is accepted.

Debit

Credit

A/P Subcontractor

6,300

A/P Retention

700

Direct Cost

7,000

02/10/12 Subcontractor is issued a check for $6,300

02/28/12 Subcontractor bills $3,350 ($3,000 current, plus 1/2 of retention)

A/P Vendor Invoice Entry to subcontractor. Invoice amount = $3,000; $300 retention defaults in A/P Vendor Invoice Entry, but is overridden with $350-

Debit

Credit

A/P Subcontractor

3,350

A/P Retention

350

Direct Cost

3,000

Spectrum will allow entry of negative retention only if the invoice is for a subcontract, and only in amounts up to the remaining retention balance on the contract.