Miscellaneous Questions

When does an A/P subcontract change order become part of committed costs?

The date entered in the Proposal date field will determine when the change order becomes part of open commitments.

Which date controls when the change order becomes part of the contract?

The Date issued field determines the date when the change order becomes part of the contract.

Which date controls when an executed change request (action types 1 or 2) become part of the contract?

The Approved date determines the date when the change order becomes part of the contract. Of course, the change request must have a status with action types 1 or 2.