Billing Retention Using Draw Request
The following example details the Draw Request process when billing retention to the customer:
Example: $100,000 contract
10% retention
Time Line 12/31/15:
Over some months, work has progressed on the project and Draw Requests have been issued monthly, with 10% retainage. At 12/31/15, $90,000 has been completed ($81,000 current, plus $9,000 retainage)
Debit |
Credit |
|
A/R Trade |
81,000 |
|
A/R Retainage |
9,000 |
|
Contract Revenue |
90,000 |
Time Line 01/31/16:
An additional $10,000 has been completed and 1/2 of the retainage is now due as well.
On the Draw Request Billing Entry screen, enter additional percent complete information as usual to generate an additional $10,000 complete.
On the Summary Billing Entry, override the 10% retainage figure with 5%. This will cause the current billed to become 95% of the total ($81,000 + $14,000 = $95,000).
Debit |
Credit |
|
A/R Trade |
14,000 |
|
A/R Retainage |
4,000 |
|
Contract Revenue |
10,000 |
Time Line 02/28/16:
The final $5,000 retainage is billed using an additional Draw Request.
On the Draw Request Billing Entry screen, the heading information is recorded but no additional percent complete is done since the job was 100% complete last month.
On the Summary Billing Entry, override the retainage figure with 0%. This will cause the current billed to become 100% of the total ($81,000 + $14,000 + $5,000 = $100,000).
Debit |
Credit |
|
A/R Trade |
5,000 |
|
A/R Retainage |
5,000 |
|
Contract Revenue |
0 |