What date determines when Projected Cost will be updated for a Change Request with Action Type #3 (cost revision)?

A: When the status is changed to an Action Type #3, the system will populate the current date into the ‘Submitted date’ field on the Dates tab.

Change Requests use the following hierarchy to determine when to impact Projected Cost:

  1. C.O. Date – First looks to see if there is a Change Order date. When no date is found, it continues down the hierarchy.
  2. Approval Date
  3. Submitted Date
  4. Current Date