Estimate Hours or Costs for a Resource

Use productivity projections to estimate hours or costs for a resource.

  1. Select the Productivity tab.
  2. Select criteria for the saved projections that you want to apply to a resource.
    Selections include the following: Entry Code Type, Resource Type,Resource Group, Company, and Job.
  3. Click to add a header row.
  4. In the header row fields, select an Entry Code and Resource No., and complete the remaining fields as needed.
  5. For each applicable job phase shown in the header row, enter estimated hours or units for the resource.
    The overall job phase projections displayed in the grid update automatically.
  6. Click Save .
The Manage Resources tab tracks resource estimates based on the job, phase, and pay period.