View the Planned Start/Finish Report

You can view the Planned Start/Finished report to see planned start and finish dates for each task in a process at each location.

You have to import dates for process tasks into Field View for them to appear in this report.
Fastpath: Process > Planned Start/Finish
  1. Confirm that the correct business unit is selected in the Current Business Is field, and that the correct project is selected in the Current Project Is field.
  2. Select Process > Planned Start/Finish.
  3. In the Process Name field, select the process for which you want to view the report.
  4. In the Issued To Organization field, select an organization to see only processes issued to that organization or select All Organizations to see processes for all organizations.
  5. In the Date From field, select the start date for the report.
  6. In the Date To field, select the end date for the report.
  7. Click View.