View the Process Performance Report

You can view the Process Performance Report to see the date each task was due to be completed and the date it was actually marked completed.

You have to import dates for process tasks into Field View for them to appear in this report.​
Fastpath: Process > Performance Report
  1. Confirm that the correct business unit is selected in the Current Business Is field, and that the correct project is selected in the Current Project Is field.
  2. Select Process > Performance Report.
  3. In the Process Name field, select the process for which you want to view the report.
  4. In the Issued To Organization field, select an organization to see only processes issued to that organization or select All Organizations to see processes for all organizations.
  5. Click View.