View a Planned Start/Finish Report

View all Process Task's start and finish dates for a Project.

  1. Click on Processes in the header.
  2. In the Ref column, select the process you want to work with.
  3. Click on the List tab.
  4. Click the Actions button and select Planned Start/Finish Report.
    The Process Start/Finish Report window appears.
  5. (Optional) If you want to see only the Process Tasks issued by or to you, clear the View All Tasks check box.
  6. (Optional) If you want to view the report in A3 format instead of standard format (8 1/2 x 11), select the Show A3 Format check box.
  7. In the Date From and Date To fields, enter the date range for planned activity.
  8. Click View Report.
    The report opens in a new browser tab or window, depending on your browser settings.
Activity scheduled within your selected date range appears in the report.