Change the Status of Multiple Process Tasks

Change the status of multiple Process Tasks at one time.

You can use this process for a single process task if you want to add a comment to indicate the reason for the status change.
  1. Confirm you're working in the correct Project and select Processes in the header.
  2. Select the check box for each Task you want to update.
  3. Click Actions and select Change Status.
    The Change Status window appears.
  4. In the Status field, select the single status to apply to all selected Tasks.
  5. (Optional) In the Status Change Comments field, enter the reason(s) for or any comments about the status change.
  6. Click Save.
The Task status is updated and a new record is added to the registry for each.
(Optional) View a history of a Task's status changes.