About the JB Progress Billing Change Orders Form
Use this form to edit, add, and remove change orders.
Access this form by clicking the Change Orders button on the JB Progress Billing form. The system automatically adds any change orders entered (in JC Change Orders) since the last billing to the current progress billing as follows:
When a billing is created automatically by JB Progress Bill Initialize, change orders with approval dates through the specified Change Orders Thru date are added to the current billing.
When a new billing is added manually in JB Progress Billing, all approved External change orders not already on another billing are added to the current billing.
Once a change order is added to the current billing, its information can be viewed and/or edited in this form. Additionally, the change order amount is reflected in the current Contract and Item amounts in the Bill Items Info section of JB Progress Billing. For more information, see About Updating Previous Billed Amounts on Future Bills.
About Adding Change Orders
Add change orders manually to this form when:
-
The system did not automatically add the change orders due to the billing date range set for the billing
-
The change order was entered in JC Change Orders after the billing was created and you want the change order included on the billing.
About Changing Change Orders
You are responsible for the timing of changes to change orders (in JC Change Orders) and including those changes on a billing invoice.
JB has no way of knowing if a change order from a previous invoice has been changed or not. Because you are allowed to make changes to change orders in JC as long as the month is open, it is possible for you to print an invoice, and then revise a change order. In which case, JB contract amounts would no longer match Job Cost. JB derives the current contract amount based on previous billings. The change in the change order would be reflected in JC but not in JB. If you have the ability to delete and re-pull the billing, the changes made in Job Cost would then be reflected on the new bill.
About Deleting Change Orders
You can delete (remove) a change order from a billing as long as the GL month is open.
Because change orders affect current contract amounts and not billed amounts, removing them from a billing will have no affect on the billing.
Deleting a Billing
You can delete a billing (using the Delete button), as long as the billing has not been interfaced.
If the billing has been interfaced, you must flag the billing for deletion by setting the Status to Delete. Once set, the system will perform a check for change orders. If change orders exist, a message displays informing you that you cannot delete a bill until the change orders have been removed. When you click OK, the JB Progress Bill Change Orders form displays so that you can remove the change orders from the billing. Once they have been removed, the JB Progress Billing form displays, where you must reflag the billing for deletion. The bill must then be re-interfaced to complete the deletion process.