About the JC Cost Projections Form
Use this form to manipulate projected units, hours, and costs.
You can have the program calculate projections for you, enter your own projections, or use a combination of both methods.
There are two versions of the cost projections feature.
-
Legacy - Prior to the version 6.8 release, all cost projections were processed using the JC Cost Projections form.
-
Enhanced - Starting in version 6.8, the application also includes an enhanced version of the cost projections process in the PM module.
You can have the program calculate projections for you, enter your own projections, or use a combination of both methods.
For information on entering cost projections, see Enter Cost Projections.
For information on PM Projections Codes, see About the PM Projection Codes Form.
Click the links below for additional information related to cost projections.
- About the Refresh Data Button
- Column Display
- About Phase Filtering for Cost Projections
- About Row Highlighting
- Cost Projection Attachments
- Uncommitted Cost Column
- About the JC Projection Options Form
- About the JC Projection Calculation Form
- About Reviewing & Updating Projections
- About the JC Projection Future CO Form
- About the JC Job Phase Cost Detail Form
- About the JC Projection Detail Insert Form
- About the JC Projection Job Close-Out Form