Buy Out

Check this box if the buy out is complete for this phase/cost type; that is, total commitments have been made through subcontracts, purchase orders, and/or material orders (applies to linked cost types as well). Initially defaults based on how you have set the Buy Out checkbox for the phase/cost type in JC Job Phases. If checked and the plugged value does not equal the buy out value (e.g. in a previous month you plugged a projected final, posted that projection, then later checked the buy out box, and now in a current projection batch have a discrepancy between the previous plugged value and the sum of Actual + Remaining Committed), the line color will change to light blue.

Leave this box unchecked if the buy out is not complete for this phase/cost type.