To Date

Enter the ending date in a range of dates to which this projection detail applies.

Date field shortcuts

T ort

Set the date to the current date.

MMDD

Four digit month and day

Enter a four digit month and date (MMDD) and the system will automatically add the current year.

+

The system will automatically set the date to tomorrow.

+5

The system will automatically set the date to 5 days in the future.

You can actually enter any value after the +, for example you can enter +7 to set the date to next week.

-

The system will automatically set the date to the previous day.

-5

The system will automatically set the date to 5 days in the past.

Just like with +, you can enter any value after the -, for example you can enter -7 to set the date to the previous week.

Why is this field disabled?

The Projection Detail tab is only enabled when the Activate projection detail feature box is checked (PM Company Parameters form, Projections tab).

The fields on the Projection Detail tab are enabled based on the JB cost type category associated with the selected cost type (JC Cost Types form, JC Cost Type Category field).

JC Cost Projections