UM

Enter the unit of measure for this projection detail line. Initially defaults the unit of measure as follows:

  • If you specified a budget code with a Costing Level of ‘Detail’ and a basis of ‘Hour’, defaults the Time UM specified for the budget code in JC Budget Codes.

  • If you specified a budget code with a Costing Level of ‘Detail’ and a basis of ‘Unit’, defaults cost type’s assigned unit of measure.

  • If you specified a budget code with a Costing Level of ‘Subtotal’ or ‘Total’, defaults as null.

  • If you did not specify a budget code, defaults the cost type’s assigned unit of measure.

    Why is this field disabled?

    The Projection Detail tab is only enabled when the Activate projection detail feature box is checked (PM Company Parameters form, Projections tab).

    The fields on the Projection Detail tab are enabled based on the JB cost type category associated with the selected cost type (JC Cost Types form, JC Cost Type Category field).

JC Cost Projections