Previous Projected Through Prior Month

Check this box to have the Previous projections column display amounts through the month prior to the current batch month (i.e. if batch month is 07/07, shows amounts through 06/07).

Leave this box unchecked to have the Previous projections column display amounts through the current batch month (i.e. if batch month is 07/07, shows amounts through 07/07).

Note: Amounts displayed will not be date sensitive. Therefore, a projection done on 07/15/07 will be included in the Previous amount for a batch created on 07/10/07.  

JC Projection Options

JC Cost Projections 6.7