Projection Method

Indicate the override projection method that will be used to calculate cost projections for this batch. Method specified here overrides the method specified in JC Company Parameters. This field initially defaults to the method that you specified in JC Company Parameters (Projection Method field, Projections tab).

  • Actual - Cost projections will be calculated using only actual costs.

  • Actual + Committed Costs - Cost projections will be calculated using both actual costs and committed costs.