Show Only Changed Since Last Projection
Check this box to display only those phases where the current calculated forecast is not equal to the previous calculated forecast. The forecast is the computer-generated calculation of projections as of the time you brought the job into the batch. It is compared to the previous calculated forecast. The previous projection may be either the last time projections were posted in the current month or the last time in the previous month, depending on whether the Previous Projected Through Prior Month box is checked.
Leave this box unchecked to display all phases on the job.