Change in Days

Display only, the total number of days by which this change order will affect the contract’s original completion date. This total is the sum of ‘change in days’ for all change order items.

If change order was interfaced from PM, this field defaults the “change in days” specified for the approved change order. If changes to this value occur due to changes made at the change order item level, this value and the modified item values will be updated to PM.

 

 