Bill Type

Indicate the bill type for this contract item. Initially, this defaults to the bill type specified for the contract (header).

  • Progress - Select this option to have costs for this item billed on a percent complete or units complete basis.

  • T & M - Select this option to have costs for this item billed on a Time and Materials basis.

  • Both - Select this option to have costs for this item billed on a Time & Materials and/or Progress basis. You might typically use this option for items you bill on a T&M  basis with a Progress backup.

  • None - Select this option if you are not billing costs through Job Billing.

Note: If you change the bill type after an item has been billed, a message displays informing you that the item has been previously billed and that the change may result in differences on the Previous Billed amounts in JB. However, record will be saved.  