Bill Flag

Specify whether units and/or costs for this cost type on this phase are to be used in calculating progress complete for progress-type billings in Job Billing.

  • Y-Units and Dollars – Both units and dollars posted to this cost type will be used to calculate progress complete.

  • C-Only Dollars – Only dollars will be used in calculating percent complete for this phase/cost type.

  • N-Neither – Neither units nor dollars posted to this cost type will be used when calculating progress complete. Phase cost types with this flag will also not be included in T & M billings.

 

 