Minimum Projection %

Enter the minimum percent complete needed to calculate a cost projection in JC Cost Projections. If the percent complete is below this minimum, then the projected costs will be calculated at the higher of estimated or actual costs.

Projection minimum percentage is set up in several places

  • PM Company Parameters / JC Company Parameters - This value is only used if a projection minimum percentage has not been set up on the project/job or phases.

  • PM Projects / JC Jobs - This value is only used if a projection minimum percentage has not been set up on the phases.

  • PM Project Phases / JC Job Phases - This field defaults based on the projection minimum percentage set up using the JC Phases form.

  • JC Phases - This is the default value of the projection minimum percentage when new phases are added to a project/job.

    What if you leave this field blank?

If there is no entry in this field, the system will use the minimum percent specified at the job level or, if not there, at the company level.

How do projections work?

Click here for an overview on projections.

JC Job Phases and PM Project Phases

This field is on both the JC Job Phases and PM Project Phases forms. When a change is made, both forms are updated.

 

 

JC Job Phases