Minimum Projection %

Enter the minimum percent complete needed to calculate a cost projection for this project/job. If the percent complete is below this minimum, the projected costs will be calculated at the higher of estimated or actual costs.

The value in this field is only used if a minimum percent complete is not set up on the phases (JC Job Phases / PM Project Phases).

Projection minimum percentage is set up in several places

  • PM Company Parameters / JC Company Parameters - This value is only used if a projection minimum percentage has not been set up on the project/job or phases.

  • PM Projects / JC Jobs - This value is only used if a projection minimum percentage has not been set up on the phases.

  • PM Project Phases / JC Job Phases - This field defaults based on the projection minimum percentage set up using the JC Phases form.

  • JC Phases - This is the default value of the projection minimum percentage when new phases are added to a project/job.

Note: Many of the fields on the JC Jobs form are also on the PM Projects form. When you make a change to this field on the JC Jobs form, the system immediately updates the same field on the PM Projects form.