About the JC Revenue Calculation Form
Use the JC Revenue Calculation form (accessed by selecting the Calculate Projections option from the Options menu in JC Revenue Projections) to initialize revenue projections.
Write Over Plugged Values
The Write Over Plugged Values option determines how the sytem handles plugged (overridden) values during initialization.
You can specify to 'Never' calculate projected revenue units and dollars for a contract item that has been previously plugged, or to ‘Always’ calculate projected revenue units and dollars for a contract item, regardless of whether previous plugged values exist.
Projection Methods
When initializing revenue projections, the projection method determines how the system calculates projected revenue values. Available methods are as follows:
- Units from
Cost Projections – If you select this method, calculation
will project revenue units based on projected cost units from JCCD (Cost
Detail). Calculation will include projected cost units for all phases/cost
types assigned to a contract item where the cost type UM equals the contract
item UM, and the cost type Item Unit Flag is checked. If cost projected
units are 0.00, projected revenue units will be set equal to the current
contract units. This method is typically used for unit-based contracts where
the contract units are likely to change, and cost projections have been done
and projected units modified (plugged).
If the unit of measure for the Contract Item is not the same as the Job Phase Cost Header (JCCH) unit of measure, revenue projected units and dollars will be calculated as follows:
Revenue Projected Units = (Cost Projected Units \ Cost Current Estimate Units) * Contract Item Current Contract Units
Revenue Projected Dollars = Revenue Projected Units * Contract Item Unit Price
Note: Cost Projected Units and Cost Current Estimate Units are based on cost types with the Item Unit flag checked. - Billed Units and Dollars - If this method is selected, calculation will project revenue units and dollars based on units and dollars billed through the month and date specified. This method is typically used at the end of a job (i.e. job closeout) when you want the revenue projected units and dollars to be equal to the billed values.
- Actual Cost plus Markup Percent – If this method is selected, projected revenue values will be set equal to actual costs plus a specified markup percent. If you do not specify a markup, projection values will be set equal to actual costs. You will typically use this method for T&M projects. Since WIP reports use projection information, this will allow revenue to be set to cost plus the specified markup on the reports.
- Projected Cost plus Markup Percent – If this method is selected, projected revenue values will be set equal to projected costs plus a specified markup percent. If you do not specify a markup percent, projection values will be set equal to projected costs. You will typically use this method for T&M projects. Since WIP reports use projection information, this will allow revenue to be set to projected cost plus the specified markup on the reports.
Include Contract Item Bill Types
This section allows you to specify which contract items (within the specified contract item range) will be included in projection calculations based on bill type. There are three options available:
- All – Use this option to calculate projections for all contract items, regardless of their assigned bill type.
- Progress – Use this option to calculate projections for only those contract items with a bill type of 'Progress'.
- T&M and Both – Use this option to calculate projections for contract items having either a 'T&M' or 'Both' bill type. You will typically select this option if you are using the 'actual cost plus markup' projection method.
After you set up the projection options, specify the contract and contract item range to initialize. Then click OK to begin calculations. Once complete, a message displays indicating how many projections were initialized. Click the Close button to exit the calculation form and return to the revenue projections grid.