Include Contract Item Bill Types
All – Select this option to calculate projections for all contract items, regardless of bill type (i.e. Progress, T&M, Both, and None).
Progress – Select this option to calculate projections for only those contract items with a 'Progress' bill type.
T&M and Both – Select this option to calculate projections for only those contract items with a 'T&M' or 'Both' bill type. You will typically select this option if you are using the 'actual cost plus markup' projection method.