Activate Projection Detail Feature

When this box is checked users can enter projection detail on phases/cost types, for example budget code, detail date range, units, hours, unit cost, etc.

This will add a Projection Detail tab to the lower portion of the JC Cost Projections form.

This option only impacts JC Cost Projections

There are cost projection settings on both the JC Company Parameters and PM Company Parameters forms. If you change an option on one form, the other form will not be impacted. For example if you make a change to the PM Company Parameters form, the JC Company Parameters form is not impacted. This allows you to maintain separate configurations for JC Cost Projections and PM Cost Projections.

There are two versions of the cost projections feature.

  • Legacy - Prior to the version 6.8 release, all cost projections were processed using the JC Cost Projections form.

  • Enhanced - Starting in version 6.8, the application also includes an enhanced version of the cost projections process in the PM module. More

    You can continue using the JC Cost Projections form, or you can transition to the new PM Cost Projections process.

Overview - PM Cost Projections

JC Company Parameters