Columns for Entry

Select which columns are enabled when entering cost projections.

  • Percent Complete — Percent complete is the actual cost divided by projected cost.

  • Over/Under — The over or under amount is projected cost minus estimated cost.

  • Remaining — The remaining cost is projected cost minus actual cost.

When any of these boxes are checked, the related fields are enabled on the Info tab in the lower portion of the JC Cost Projections form.

This option only impacts JC Cost Projections

There are cost projection settings on both the JC Company Parameters and PM Company Parameters forms. If you change an option on one form, the other form will not be impacted. For example if you make a change to the PM Company Parameters form, the JC Company Parameters form is not impacted. This allows you to maintain separate configurations for JC Cost Projections and PM Cost Projections.

There are two versions of the cost projections feature.

  • Legacy - Prior to the version 6.8 release, all cost projections were processed using the JC Cost Projections form.

  • Enhanced - Starting in version 6.8, the application also includes an enhanced version of the cost projections process in the PM module. More

    You can continue using the JC Cost Projections form, or you can transition to the new PM Cost Projections process.

 

 