Post Crew With Progress Entry

Check this box if you will be posting progress to crews in Progress Entry. When posting progress to crews, units produced are entered by job/phase/cost type/crew code. This information can be used to create crew productivity reports.

Leave this box unchecked if you will not be posting progress to crews. Instead, progress will be posted by job/phase/cost type.