Post Projection Forecasts when only Forecast exists

When this box is checked users can post projections even if only the forecast has changed, for example the projections did not change for the phase/cost type, but the actual costs caused the forecast to change.

This option only impacts JC Cost Projections

There are cost projection settings on both the JC Company Parameters and PM Company Parameters forms. If you change an option on one form, the other form will not be impacted. For example if you make a change to the PM Company Parameters form, the JC Company Parameters form is not impacted. This allows you to maintain separate configurations for JC Cost Projections and PM Cost Projections.

Overview - Cost Projections

JC Company Parameters