Link Progress Cost Type

Enter a cost type code to link a cost type or press F4 to select a cost type from a list.

The cost type selected in this field should be the primary cost type. For example if labor should be the primary cost type and burden should be the secondary cost type, open the burden cost type and select the labor cost type in the Link Progress Cost Type field. When a plugged value is entered on the labor cost type (JC Cost Projections or PM Cost Projections ), the burden cost type will also be updated.

Click here for detailed information about linking cost types.

Using linked cost types

JC Cost Types