Bill Flag

Specify whether units and/or costs for this cost type on this phase are to be used in calculating progress complete. Used only for Job Billing.

Y = Both units and dollars posted to this cost type will be used to calculate progress complete.

C = Only dollars will be used in calculating percent complete for this phase/cost type.

N = Neither units or dollars posted to this cost type will be used when calculating progress complete. Cost types with this flag will also not be included in T & M billings.

Note: The standard bill flag may be changed for a specific phase in JC Job Phases.  

JC Phases