Minimum Projection %
Enter the minimum percent complete needed to calculate a cost projection in JC Cost Projections. If the percent complete is below this minimum, then the projected costs will be calculated as the higher of the estimated or actual costs.
Projection minimum percentage is set up in several places
PM Company Parameters / JC Company Parameters - This value is only used if a projection minimum percentage has not been set up on the project/job or phases.
PM Projects / JC Jobs - This value is only used if a projection minimum percentage has not been set up on the phases.
PM Project Phases / JC Job Phases - This field defaults based on the projection minimum percentage set up using the JC Phases form.
JC Phases - This is the default value of the projection minimum percentage when new phases are added to a project/job.