Phase

This field only displays when 6-SM Work Order is selected in the Type field and the specified SM work order is job-related.

The system only enables this field if you specify a work order scope that is not assigned a phase (in SM Work Orders).

Enter the phase (from JC Job Phases) to which this purchase order item applies. Press F4 for a list of valid job phases.

  • If you specify a work order scope that is assigned a phase, this field defaults the scope phase and cannot be changed.

  • Phases entered on a PO item for an SM work order must be set up for the job in JC Job Phases, regardless of whether phases on the job are locked. If you need to add a phase "on the fly", you can do so by pressing F5 to access JC Job Phases. Once you add the phase to the job and exit JC Job Phases, you can enter the phase here.