Field Definitions: JC Job Phase Cost Detail Form
The following is a list of field descriptions for the JC Job Phase Cost Detail form. Many of the descriptions include links to other topics that provide additional information about or related to the topic.
Phase
Cost Type
Begin/End Month
Show Actual Units Only
Costs
Specify the type of costs to display in the detail grid below. Then click Refresh Grid to reload the grid with the selected values.
Actual – Select this option to show all actual costs for the selected job/phase/cost type.
Committed – Select this option to show all committed costs for the selected job/phase/cost type.
Estimate – Select this option to show all estimated costs for the selected job/phase/cost type.
Projected – Select this option to show all projected costs for the selected job/phase/cost type.