About Auto-Setting Remaining Unit Cost
When updating projections in JC Cost Projections, you can have the system automatically set the remaining unit cost for a selected phase/cost type to the current estimated unit cost or actual unit cost.
To have the system set remaining unit costs for phases/cost types, click the Set Remain UC button (below grid). The system sets the remaining unit cost based on the Select Which Unit Cost to Use for Remaining drop-down option selected in JC Company Parameters (Projections tab). If you selected ‘E-Current Estimate’, the system sets the Remaining U/C column equal to the Current Est’d U/C column. If you selected ‘A-Actual’, the system sets the Remaining U/C column equal to the Actual U/C column.