About the PM Subcontract Change Orders Form

Use this form to record a change in scope to an existing subcontract - for example additions or subtractions to existing items, or the creation of new scope items. Use this form to create and maintain subcontract change orders (SCOs/SubCOs), generate and send an SCO document to a list of contacts using the Create and Send feature, and then approve the SCO.

What do you need to know?

  • You cannot create new subcontracts using this form - You cannot use this form to create new subcontracts, but you can create new subcontract items using the SL Item field in the lower portion of the form. Click here for a basic overview on creating new subcontracts.

  • You can create new subcontract items - When you add items to an SCO, you are actually creating new subcontract(SL) items. For example, after you create a new SubCO item using PM Subcontract Change Order, you can open PM Subcontracts and view the SL item that was created using the Non-Interfaced tab.

  • You cannot create a change order for back charges or add-ons - Only subcontract items with an item type of Regular or Change can be included on a subcontract change order, which means that you cannot create change orders for subcontract items that are back charges or add-ons. Click here for a brief description of subcontract item types.

Subcontract Totals

The Totals tab displays the subcontract amounts. The formulas used to calculate the totals are listed below. All of the totals on this tab include taxes.

Total TypeDescription
Original SubcontractOriginal Cost + Original Tax

This amount only includes regular and add-on subcontract item types.

Prior Approved Change OrdersA change order item must meet all of the following conditions before it will be included in this amount:
  • Associated with a subcontract change order number that is less than the current subcontract change order number (Subcontract CO field in the upper portion of PM Subcontract Change Orders)
  • The Interface box is checked on the Info tab in the lower portion of PM Subcontract Change Order
  • Either assigned to an ACO or on a subcontract change order with a final status (Status field on the Info tab of the header of PM Subcontract Change Orders)
  • Associated with a subcontract change order that has the Ready for Accounting box checked on the Info tab in the upper portion of PM Subcontract Change Order
  • Not interfaced with the accounting modules using PM Interface
  • OR if the item has been interfaced with the accounting modules, none of the conditions above need to be met and the subcontract change order item will be included in the total

This amount does not include:

  • Back charges - subcontract items with an item type of back charge
Current SubcontractOriginal Subcontract + Prior Approved Change Orders
Pending Sub COTotal of the current SubCO including calculated tax
Pending SubcontractCurrent Subcontract + Pending Subcontract
Other Pending Sub COs

Subcontract change order items must meet all of the following requirements to be included in this amount:

  • Have the Interface box checked on the Info tab in the lower portion of PM Subcontract Change Order
  • Subcontract change order number that is less than the current subcontract change order (Subcontract CO field in the upper portion of PM Subcontract Change Orders)
  • On a subcontract that has not been approved, or has been approved but does not have a final status (Status field on the Info tab of the header of PM Subcontract Change Orders)

This amount does not include:

  • Back charges - subcontract items with an item type of back charge

  • Subcontract items assigned to an ACO or interfaced with accounting