PM Copy Project Form
Use this form to use an existing project to create a new one. This can save you time if you need to create a new project and a similar one already exists.
Once the copy process is complete, a message displays telling you the job was successfully copied. If an error occurred during the copy process, a message displays with information about the error. A second message is then displayed informing you that the copy was not completed.
Data Groups
The ‘Groups’ section is an informational display showing the vendor, customer, tax, phase, and material groups for the source and destination companies.
If the source and destination companies differ, chances are the data groups will also differ. This can create problems when copying data that relies on the specific data groups for valid information. For example, if the phase groups differ, then phases being copied from the source project may not exist in the destination company. For this reason, the system does not specific tables and the data within those tables when certain data groups differ. The following describes what information is not copied when the source and destination data groups differ:
Group |
Data Not Copied |
---|---|
Vendor |
Vendor, firm, firm contact, or project firms |
Customer |
Affects only the customer assigned to destination contract. If you do not specify a customer for the new contract, and the customer assigned to the existing contract does not exist in destination company, the customer will not be copied to the new contract. |
Tax |
All data in tax-related fields |
Phase |
Phase and cost type information, which includes project markups, job phases, cost type headers, subcontract detail, material detail and change order detail. |
Material |
Material code - only applies when copying material detail. Material detail records are copied without their associated material codes. |
Information to Copy
The Copy Amounts section allows you to specify whether to copy all amounts (original and current estimates) or to copy the original estimates only. You can also specify to not copy any of the amounts to the new project.
The Additional Information to Copy section provides options for copying project-related detail, such as subcontract detail, material detail, project firms, and change order detail. If data groups differ between source and destination companies, some of these options will be grayed out.
- If phases are locked for the source project, they will also be locked for the destination project.
- With the exception of the PR State Code, the payroll information defined for the source project (PR Info tab in PM Projects) will not be copied to the new project. You must set that information up manually.
- If you do not select to copy contract item retainage, the new contract items will default the retainage percent defined for the contract during the copy process.