PM Project Add-Ons Form
Use this form to input project add-ons. You can open this form in two ways:
-
Double-clicking in a grid row on the Add-Ons tab of PM Projects
-
Highlighting a grid row and selecting Open Related Record in Form from the Records menu.
You can also enter add-on information directly into the grid using the Add-On tab in PM Projects.
The system will automatically add any add-on costs to the project that are set up for the company in PM Company Parameters (Add-ons tab). You can modify or delete these default add-ons if needed, but only standard add-ons (those with the Standard check box selected in PM Company Add-ons) are including on every pending change order when they are created in PM Pending Change Orders.
Add-On Basis
For each project add-on, you must specify the basis for the add-on; that is, the amount on which to base the add-on cost. You can specify to use a flat amount or have the calculation based on a percentage of the overall change order or the total costs for a specific cost type.
If the add-on is for additional costs (e.g. bonds), you can redirect the costs to a specific phase/cost type and/or contract item. If you wish to distribute the add-on amount to all phases on a change order with a specific cost type, leave the phase blank and enter only the desired cost type. The system will distribute the add-on amount proportionally to all phases on the change order with that cost type, adjusting the last phase/cost type for rounding (if necessary).
Example:
Add-on |
100 |
Basis |
Cost Type |
Basis CT |
1(Labor) |
Percent |
10.00 |
Redirect CT |
7(Burden) |
Redirect Phase |
(blank) |
Pending CO: |
Phase |
CT |
Amount |
Add-on Amt |
|
02210- - |
1 |
300.00 |
30.00 |
|
03310- - |
1 |
300.00 |
30.00 |
|
04410- - |
1 |
400.00 |
40.00 |
Total: |
$1000.00 |
$100.00 |
Approved CO: |
Phase |
CT |
Amount |
|
02210- - |
1 |
300.00 |
|
|
7 |
30.00 |
|
03310- - |
1 |
300.00 |
|
|
7 |
30.00 |
|
04410- - |
1 |
400.00 |
|
|
7 |
40.00 |
Total: |
$1100.00 |
Add-On Total Type
This section is used to specify the add-on type, which determines how the add-on will be calculated.
-
Net Total – This add-on type is calculated first, and will be based on either Cost, Cost plus Markup, or Total, depending on the ‘Net Add-On Calculation Level’ selected (see below).
-
Sub Total – This type of add-on will calculate an add-on amount based on the net amount plus markups plus net total add-ons. Sub total add-ons do a cycle calculation 5 times to provide the most accurate add-on total.
-
Grand Total – This type of add-on will calculate an add-on amount based on the net amount plus markups plus net total add-ons plus sub total add-ons.
Add-ons defined here are automatically set up and calculated for each item you enter on a change order. Calculations are based on the item's net amount and the add-on type. Net total add-ons are calculated first, then sub total add-ons, and lastly, grand total add-ons.
Net Add-On Calculation Level
This option is used in conjunction with the Net Total add-on type and allows you to specify the amounts on which to base the add-on calculation. Options are as follows:
-
C-Cost – Calculation is based on net amount only.
-
M-Cost plus Markup – Calculation is based on net amount plus markups.
-
T-Total – Calculation is base on net amount, plus markups, plus lower sequential add-ons.
Revenue
Use this section to redirect add-on revenue to a separate contract item (when approving pending change order items). Once you check the Re-direct Add-on Revenue When Approved option, you will need to specify the contract item to which you are redirecting the add-on amount. If you specify a contract item that does not exist for the contract, it will be added once the ACO Item is generated. The contract item description will default from the add-on description, the UM will be set to LS, and the amounts will be set to 0.00.
Pending change orders can only point to a single contract item; redirecting an add-on to a separate contract item will therefore require that a separate change order item be created. The Create ACO Item option allows you to specify the numbering method to use when creating ACO items:
-
Use Revenue Item – This option will create an ACO item number equal to the specified Revenue Contract Item number.
-
Sequential – This option will generate a sequential item number based on a specified Start at ACO Item # value.
-
Fixed – This option allows you to use a specific ACO item number.
When approving a pending change order/item, the type of change order item determines how the system handles the revenue add-on amount. If a ‘pending’ amount (item amount changes based on markups, add-ons, and phase detail), the system will deduct the add-on amount from the original PCO item. If a ‘fixed amount’ item, the add-on amount is not deducted from the PCO item amount.