About the PM Subcontract Detail Form
Use this form to set up subcontract detail information.
- If accessed from the main menu or PM Project Phases, grids display original subcontract detail records (Record Type ‘O-Original’)
- If accessed from PM Approved Change Orders, grids display approved change order subcontract detail (Record Type ‘A-Approved CO’s)
- If accessed from PM Pending Change Orders, grids display pending change order subcontract detail (Record Type (P-Pending CO’s).
You can set up subcontract detail manually, by setting up change order phases (via PM Pending Change Orders or PM Approved Change Orders) where the cost type is equal to the cost type specified for subcontracts in PM Company Parameters, or by import from third-party estimating software (using PM Data Import). If importing estimate detail, phases with subcontractor costs are automatically set up here.
Typically, phases entered in this program will be those assigned a Subcontract cost type. However, you can also enter phases for subcontract issue that are assigned cost types other than Subcontract. For example, you may have material orders, equipment leases, and so forth, where you require contracts containing more detail than purchase orders allow.
Non-Interfaced/Interfaced
The Non-Interfaced tab displays all items that have not been interfaced to the accounting modules and is used to set up/edit subcontract detail. Once a subcontract detail item is interfaced, it is moved over to the Interfaced tab and cannot be edited or deleted. If you need to change the dollar amounts for an interfaced subcontract, create a subcontract change order. Click here for more information on subcontract change orders.
In order to include subcontract detail when interfacing the project or pending/approved change orders for the project, you must check the Send box for each phase that is ready to be interfaced. Interfaced subcontract detail updates the Subcontract Ledger module.
If the Allow adding new subcontract item during subcontract change order entry box in PM Company Parameters is selected, you can add a new subcontract item to an approved or pending change order on this form (Non-Interfaced tab). When you add a new item record to the grid, the system displays a message asking if you want to add this item to allow for pre-billing. If you select Yes, the system adds the subcontract item with 0.00 amounts to the existing subcontract. This enables you to invoice against this item , even without the original estimate being established. When you interface to SL, the system will then record the original and current amounts to the item. If you select No, the item record remains in the grid, but the item is not added to the subcontract and you will not be able to invoice against the item.
Subcontract Numbers
You can enter subcontract numbers manually or you can click the Initialize button to automatically generate them.
Enter the subcontract numbers manually - If you are assigning a new subcontract number, you must first assign a vendor to the item. If you are assigning an existing subcontract number, the vendor number is not required because the system will automatically default the vendor from the subcontract header set up in PM Subcontracts.
Automatically assign the subcontract numbers using the Initialize button. The Initialize button automatically generates subcontract numbers based on the Subcontract Format Options you defined in PM Company Parameters. However, for this option to work, you must assign a vendor to each applicable phase/cost type sequence. The system skips any phase/cost types that do not have a vendor assigned. If a subcontract already exists for a vendor, the system assigns the phase/cost type sequence as an item on the existing subcontract.
If the Initialize button is disabled and you are entering a change order, the Disable Initialize button for change order subcontract detail box in PM Company Parameters is probably checked. This means that you have to manually enter subcontract items.