Seq

Enter N, New, or + to add a new material or category override sequence. The system will automatically assign the next available sequence number.

Category

Enter the category for which you are setting up the override markup or discount rate or leave blank if this override sequence applies to a specific material; you cannot specify both a category and a material for an override sequence.

Note: Material and category overrides set up in this form at the service site or customer levels, will override those set up at the rate template level, respectively.

Material

Enter the material for which you are setting up the override markup or discount rate or leave blank if you specified a category (above) for this override sequence; you cannot specify both a category and a material for an override sequence.

Note: Material and category overrides set up in this form at the service site or customer levels, will override those set up at the rate template level, respectively.

SM Cost Type

SM Cost Type field on the SM Rate Override Material (Category & Material Overrides tab) and SM Override Category Material form.

Enter the SM cost type to apply override rates towards. Press F4 for a list of available SM cost types from which to choose.

Type

Specify the rate type for this material or category override sequence.

  • Markup - Select this option if the Percent specified below represents a markup rate.

  • Discount - Select this option if the Percent specified below represents a discount rate.

Note: Material and category overrides set up in this form at the service site or customer levels, will override those set up at the rate template level, respectively.

Basis

Select the cost basis for this category or material override sequence. The basis selected here will be used in billable rate calculations when entering materials on a work order that reference the specified material or category.

  • A - Actual Cost — Select this option to use the actual cost of the part (i.e. the Cost Rate).

  • S - Standard Cost — Select this option to use the Std Unit Cost defined for the material in IN Location Materials (Inventory lines) or HQ Materials (Purchase lines).

  • V - Average Cost — Select this option to use the Avg Unit Cost defined for the material in IN Location Materials (Inventory lines) or HQ Materials (Purchase lines).

  • L - Last Cost — Select this option to use the Last Unit Cost defined for the material in IN Location Materials (Inventory lines) or HQ Materials (Purchase lines).

  • P - Standard Price — Select this option to use the Std Unit Price defined for the material in IN Location Materials (Inventory lines) or HQ Materials (Purchase lines).

    Note: If the unit of measure specified for the work completed material line does not match the Standard UM defined for the material (in HQ Materials), the system will use the unit cost or unit price (if using Standard Price) defined for the posted unit of measure in the Add'l UMs table (Inventory lines) or Additional Units of Measure table (Purchase lines).
Note: Material and category overrides set up in this form at the service site or customer levels, will override those set up at the rate template level, respectively.

Break Points By

Select how to apply rate break points when calculating discounts or markups for stocked or purchased materials specified on a work order using this template.

  • T-Total Cost - Select this option to apply rate break points based on the total cost of the material. For example if you have a break point value of $500, the system will apply a markup or discount when the material total is equal to or greater than $500.

  • U-Unit Cost - Select this option to apply rate break points based on the unit cost of the material. For example if you have a break point value of $10, the system will apply a markup or discount when the material's unit cost is equal to or greater than $10.

Percent

Enter the standard markup or discount percent to apply when work completed inventory or work completed purchase lines on a work order reference this material or category (e.g. enter 5% as 5.00000)

The system will use this rate when determining the billable rate for the work completed line.

  • This field initially defaults as 0.00. If you leave the value at 0.00, the system assumes that you intended this value and no markup or discount rate will be applied to the work completed line for the specified material or category; no further rate search will occur.

  • Material and category overrides can be set up at the rate template, effective date, customer, and service site levels; therefore, the system will use a specific hierarchy to determine which rates to use. For more information, see Material Rate Hierarchy.

Break Point Value

Enter the amount to use as a break point when applying discounts or markups to stocked or purchased materials specified on a work order. The system will apply a markup or discount rate (depending on the rate type selected for the material or category) using the percentage specified to the right.

The option you selected in the Break Point By field for the category or material determines what the break point value represents. If you selected Total Cost, the system will apply the specified percentage when the total cost of the material reaches this amount. If you selected Unit Cost, the system will apply the specified percentage when the unit cost of the material reaches this amount. For more information about rate break points, see Rate Break Points.

Note: Rate break points set up by material or category in this form at the service site or customer levels, will override those set up at the rate template level, respectively.

Percent

Enter the percent to use for applying discounts or markups (depending on the rate type for the material or category) to stocked or purchased materials on a work order (e.g. enter 5% as 5.00000).

The system will apply this percentage when the total cost or unit cost of the material (depending on the Break Points By option selected for the rate template) reaches the amount specified in the Break Point Value field for this entry.

For information about how the system uses rate break points when calculating the discount or markup rate for materials on a work completed line, see Rate Break Points.

Note: Because material rates/overrides can be defined at the rate template, effective date, customer, service site, and work order quote levels, the system will use a specific hierarchy to determine which material rates to use. For more information, see Material Rate Hierarchy.