JC Work in Progress by Gross Profit

You can use the JC Work in Progress by Gross Profit report by selecting Job Cost > Reports > JC Work in Progress by Gross Profit.

JC Work in Progress by Gross Profit lists contracts and their contract amount, estimate cost at completion, gross profit, gross profit %, billings to date, actual costs, % completed, gross profit to date, billings in excess of costs, costs in excess of billings, gross profit prior year and gross profit this year.

Report Parameters

Description

Company

Accept the default, or press F4 to select a company.

Beginning Contract

Select the Field Lookup button or press F4 to select the beginning contract.

Ending Contract

Select the Field Lookup button or press F4 to select the ending contract.

Through Month

Enter through month (MM/YY).

(O)pen, (S)oft Closed, (C)losed, or (A)ll Jobs

Enter O, S, C or A.

Beginning Closed Month

Enter beginning closed month (MM/YY)

Ending Month

Enter ending closed month (MM/YY)

Beginning Department

Select the Field Lookup button or press F4 to select the beginning department.

Ending Department

Select the Field Lookup button or press F4 to select the ending department.

Sort by Department?

Check box to sort by department.

TM Contracts Only?

Check box to show T&M contracts only.

If Closed Jobs Only: Beginning Closed Month Ending Closed Month

Enter beginning closed month (MM/YY)

Enter ending closed month (MM/YY)