Preventive Maintenance Data Conversion
Below is a summary of the steps needed to complete installation. It is important that these steps be performed in the order listed.
Conversion Summary
- Complete the Preventive Maintenance Installation screen. Install the Equipment Control module, if not already installed, following instructions in the Equipment Control Help file and the Getting Started guide.
- Set the processing date to the conversion date using Processing Date Change.
- Set the processing dates to the new period using Processing Date Change.
- Enter the equipment types, if necessary. These codes were set up during Equipment Control conversion, using Equipment Type File Maintenance.
- Print the equipment type file listing and review for accuracy.
- Print the fuel/oil file listing and review for accuracy.
- Enter equipment information, if necessary, using Equipment File Maintenance.
- Print the Equipment File Listing and review for accuracy.
- Enter the individual Preventive Maintenance tasks in P.M. Tasks Maintenance.
- Print the Task File Listing and check for accuracy.
- Enter a category for parts using Category File Maintenance.
- Enter parts used for equipment repairs in the Inventory Item File Maintenance screen.
- Print an Inventory Item File Listing and check for accuracy.
- Enter the schedule at conversion using Maintenance Schedule Entry.
- Print a P.M. Tasks Maintenance Listing and check for accuracy. If some pieces of equipment have similar maintenance needs, they may be copied using Copy P.M. Schedule.
- Enter outstanding equipment work orders as of the conversion date using Equipment Work Order Entry.