Sync Job Phase and Cost Type Records Between Spectrum and ProjectSight
Create a new job phase with cost estimates and sync this data so it flows between Spectrum and ProjectSight.
- All the jobs you want to integrate between Spectrum and ProjectSight must use the same job phase format.
- Only the budget items with an Approved status are sent to Spectrum. Budget items created in Spectrum display as Approved in ProjectSight.
-
You can create a budget record in either Spectrum or ProjectSight, and, with the appropriate approved workflow status, the data will automatically create a new record in the other application. However, once budget records have been created and exist in both platforms, you must make all edits in ProjectSight. Changes made in Spectrum will be overridden, as the budget item edits and transfer amount data flows from ProjectSight into Spectrum.
Spectrum Job Phase Field Name | ProjectSight Budget Item Field Name |
---|---|
Phase Cost Type |
Budget Code |
Original Cost |
Original Budget |